This is intended to be a repository of (mostly semi-private) information about Cyert B6.

CAD drawings

Pictures

Fire Suppression

Until February 2007, the machine room had a Halon 1301 system, at which point it was replaced by an FE-25 (branded HFC-125) system. Fun links:

Cooling

Until 2005(?) the machine room had an old EDPAC air conditioner.

B6 is currently cooled by a Liebert Challenger 3000 (chilled water, infrared humidifier)

History

B6 shall always be B6. B7 is and always shall be the adjacent (non-cclub) room. Anything to the contrary is a lie.

Brief timeline as best known by contributers

MembersOnly/B6 (last edited 2011-11-19 02:50:44 by lroop@CLUB.CC.CMU.EDU)